Construction process

Knowing what to expect can help to ease some of the anxiety of the home building process. We have put together the following steps we follow when building a new home for our clients.

Although the specific sequence of construction steps varies and overlaps, we generally build your home in the following order:

-Draft the plans for your home

-You review plans and approve

-Apply for Development & Building Permit

-Application for Architectural Approval

-Create final plans for home – you review and approve

-Receive Permit and Architectural Approval

-Survey – Stake Out

-Excavation

-Form and pour footings

-Form/Pour foundation walls

-Perimeter drainage (weeping tile installation)

-Waterproofing

-Foundation inspection

-Backfill

-Grade beam (if applicable)

-Framing first floor

-Framing second floor (if applicable)

-Roof trusses

-Roof sheathing

-Install windows & doors

-Framing inspection

-Rough-in plumbing

-Plumbing inspection

-Rough-in heating

-Mechanical inspection

-Rough-in electrical

-Electrical inspection

-Shingles

-Wall insulation

-Vapour/Moisture barrier installation

-Insulation inspection

-Complete exterior services

-Siding/Stucco wire

-Pour basement floor

-Drywall main floor

-Gas meter installation & inspection

-Frost wall installation

-Framing and rough-ins for basement development (if applicable)

-Begin taping

-Complete texture

-Supply & install finishing (doors, casings & underlay)

-Cabinets Interior paint

-Final electrical

-Lino/Tile installation

-Final plumbing

-Install second finish (baseboards & locks)

-Install carpet

-Final cleaning

-Paint touch-ups

-Final/Occupancy inspection

-Homeowner Orientation with Site Superintendent

-Closing & key release with Sales Administrator